SAMPLE ASHRAE UNDERGRATED SENIOR PROJECT GRANTFUND EXPENDITURES FOUND

School              ASHRAE UNIVERSITY
Project Title     Builed Refrigeration Cycle Demonstrator for Use in Engineering Lab


ITEM………………………………………………………………………………Budget
(1) 1/6 HP Compressor………………………………………………………………………………$150.00
Pyrex Pipe and Fittings……………………………………………………………………………..$350.00
Flanges and O-Rings………………………………………………………………………………$100.00
Valves………………………………………………………………………………$125.00
Mounting Stand………………………………………………………………………………$100.00
Buts, Bolts, Hardware………………………………………………………………………………$50.00
Refrigerant 123 Charge………………………………………………………………………………$90.00
Duplication & postage………………………………………………………………………………$25.00
Miscellaneous………………………………………………………………………………$10.00
Total………………………………………………………………………………$1,000.00